Finish Electrical Phase

Finish electrical work began on Jun14, 2021 with installation of the recessed lighting in the hallway and Narthex. The electricians also got our HVAC system going again after a severed wire in the saw-cutting phase apparently cut power to three HVAC units. They also worked on the attic lights to get them all on one switch. We need to move some furniture so they can access the ceiling lights in the youth room to get them all on the same switch.

 

On June 16, the Electrician Boss was back to clean up a few loose ends. He wired all of the attic lights onto the same switch. He got the ceiling lights in the Youth Room on the same switch. and he installed the rough electrical wiring for the restroom lighting (6 boxes). He also looked at a problem we had with HVAC condenser #2. He checked and it had power to it, so the issue is not an electrical one but an HVAC issue now.

 

On June 21, the Electrician was back again to install the overhead lights in the restroom ceilings. He also wired the ventilation fan into the light switch for each restroom. It’s great to have some lights and quiet fans in the restrooms again!

 

On June 30, the Electrician was back to install the new restroom sconce lights and a motion switch in the Men’s restroom. He also electrified the bi-level drinking fountain and added white outlets and faceplates in the Kitchen to match the white tile.

 

Re-routed HVAC Power Lines video (0:30) – June 14, 2021

 